ResNet: Phase 4 (1996)
- Two buildings housing 1050 graduate students
- Following same model as Phases 2 & 3
- Full planning cycle, shortened implementation period (7 weeks, no buffer)
- Some early work begun in March
- One general contractors (from before); new wiring contractor under general contractors control (10% premium for this)
- Per port switched ethernet!