ResNet: Phase 3 (1995)
- Five buildings housing 1150 undergraduates and 100 graduate students
- Following same model as Phase 2
- Severely shortened planning cycle due to change in University leadership
- Economized on conduit use, paying the price on wiring (clean-up persists into 1996)
- Two general contractors (1 old, 1 new); old wiring contractor who had some resource problems
- 10 weeks to complete implementation, 3 week "buffer"
- 4,500 students total wired by September '95