ResNet: Phase 1 (1993)
- Five buildings housing 1,500 undergraduates
- Over 1,900 wall plates in all
- Separate contracts for construction, wiring, & video
- 10 weeks to complete implementation, 3 week "buffer"
- But...
- Serious construction issues, including cost
- EIA/TIA 568 wiring spec & local contractors
- Neither Bell nor local CATV operator were low bidder
- SMATV required "separate" wiring plant
- Inadequate funding to activate all Ethernet ports
- Student Services
- Outcomes